Planned Maintenance Notification Maintenance: DC5 – ACI Hardware & Software Upgrade 10th April 2025
As part of our commitment to quality and continual improvement, iomart will be carrying out maintenance on Thursday, 10th April 2025.
The work will specifically involve the network in Data Centre Maidenhead (DC5). We are writing to inform you of our intention to carry out this maintenance.
What will happen?
During the maintenance window the resilient border nodes will be undergoing cable maintenance with minor reconfigurations to allow for further upgrades and platform expansion.
When will the work be carried out?
The maintenance work will commence at 23:00 (BST) on Thursday, 10th April 2025 and last until 04:00 (BST) on Friday, 11th April 2025.
Who will be completing the work?
All updates to the DC5 devices will be carried out by our iomart network team.
Will I experience downtime?
Due to multiple levels of resiliency in the DC5 Data Centre Switching Fabric there is no expected interruption to services within DC5.